- 1st floor beams in place, internal block work
- Lateral straps to corners, every 1.5m horizontal intervals
- Lateral straps from floor to gable (3 joists) across at 1m intervals
- Take down peak of gable - after years of this standing monumentally proud, it looks strange now its not there!
- Bonding new and old as I type!
So as I feel 2 weeks behind, the next month will be a sprint, that is of course if the joinery/stairs and window manufacturers ...and...get back to me with the quotes! These people are so lucky that they have soooo much work in a recession!